Flying Inside an Operating Facility: the Approvals That Set Your Date

Why a drone inspection inside a running Alberta plant, mine or terminal is scheduled by the approval chain rather than the flight. Permit to work, contractor prequalification, orientation, simultaneous operations, escorts and isolations, which approvals run in parallel and which one usually sets the date.

Published 2026-11-04 · UAV Imaging Inc.

Key takeaways

A drone inspection of a flare tip, a stack, a cooling tower, a tank roof or a structure inside a running facility takes a fraction of a day in the air. Clients are routinely surprised that it takes weeks to arrange. The reason is not aviation. It is that an operating site is a controlled environment, and a contractor entering it to do non-routine work at height passes through a chain of approvals that exists whether the work is done by a drone, a rope crew or a scaffold.

Understanding the chain is worth something, because most of the delay is avoidable. The items that take time are known in advance, several of them run in parallel, and the one that usually sets the date is the one nobody asks about at the start.

What is actually in the chain

The specifics vary by operator, but the shape is consistent across Alberta plants, mines, terminals and utilities:

Only the last item is specific to flying. Everything above it applies to any contractor doing any non-routine work, which is why experienced clients find this familiar and first-time clients find it surprising.

Prequalification is the long lead item

If a drone contractor has never worked for the operator before, prequalification is almost always the item that sets the date. It is a one-time cost for the relationship and it does not depend on the scope of work, which means it can be started before the scope is finalised and frequently is not.

The reason it takes time is that it involves a third party, a document review and sometimes a queue. The documents themselves are straightforward for an established contractor, meaning certificates of insurance with the right limits and endorsements, WCB clearance, safety programme documentation and incident history. The time goes into review cycles rather than preparation.

The practical implication for a buyer is that the first question in a scoping conversation should be whether the vendor is already approved at the site. A vendor who is already in the system can often be on site in a fraction of the time, and that is a legitimate reason to prefer one over another on a time-sensitive scope.

Permit to work needs a described task

A permit is issued against a specific task in a specific area for a specific period. The area authority signing it has to be able to picture what will happen and what could go wrong. That makes vagueness the enemy of a quick permit.

A scope that permits easily says what will be flown, where the aircraft will take off and land, what altitude band it will occupy, where the crew will stand, what the exclusion area is, how long it will take, and what the crew will do if something goes wrong. A scope that says a drone inspection of the unit does not give the signer anything to assess, and the result is a conversation rather than a signature.

This is also where an experienced contractor earns their keep. The hazards an area authority will ask about are predictable, and they include loss of control near equipment, loss of link, battery fire, dropped objects, distraction of operating staff, and interaction with radio or control systems. Having written answers already in the safe work plan turns a review into a formality.

Simultaneous operations decide the day

Approvals get you onto the site. Simultaneous operations decide which day and which hour. Inside an operating facility, a drone flight is a low priority activity competing for the same airspace and ground as work that cannot be moved:

The right posture is flexibility rather than insistence. A crew that can shift to a different part of the scope, or come back the following morning, gets the work done. A crew holding out for a specific window on a busy unit gets stood down.

Escorts, orientation and the hours they consume

Most operators require an escort for contractors in process areas, and the escort is one of their own people with other responsibilities. That has two consequences worth planning for. The escort's availability is part of the schedule, and the escort's time is a real cost to the client even when it does not appear on an invoice.

Orientation is similar. It is required for every person entering, it is usually scheduled rather than on demand, and it has a validity period that can expire between visits on a repeat programme. On a multi-visit scope it is worth checking whether the orientation will still be valid for the second visit.

These are not obstacles to argue with. They are site policy and they consume hours. The useful response is to plan the day around them, which usually means fewer productive flight hours per site day than a client expects, and to raise that in scoping rather than discovering it on site.

Confined space keeps all of its requirements

A collision-tolerant drone flying inside a vessel, a tank, a stack, a silo or a duct removes the need for a person to enter. It removes nothing else.

The space still has to be isolated, drained, purged and atmospherically tested. The entry permit system still applies, because the crew is working at the opening. The attendant, the rescue plan and the communication requirements stay in place. What changes is that the time inside the space is spent by an aircraft rather than a person, which is a substantial safety gain and a substantial cost saving where it replaces scaffold or rope access.

Two scheduling consequences follow. First, internal capture is tied to the space being open and isolated, which on most assets means an outage. Second, a radiometric thermal camera needs a temperature differential to detect anything, and a vessel that has been cold and depressurised for days does not provide one. Thermal work belongs on equipment under load, which is a different window from internal visual capture.

The people you cannot clear

Flying over a public area is partly a problem of keeping people out. Inside a fence line that approach does not transfer. The people present are staff doing their jobs in their own workplace, they cannot be removed from an operating unit, and the work they are doing is often the reason the site is running.

So the mitigation shifts from exclusion to coordination. That means a notified flight with the area supervisor, routing that keeps the aircraft away from occupied work areas and walkways, a defined landing area that is not a traffic route, a spotter watching the ground rather than the aircraft, and a crew that can hold or land on a radio call. It is slower than flying an empty site and it is the trade for being inside a facility at all.

Running the approvals in parallel

The reason a well-run job takes weeks and a badly run one takes months is sequencing. Several items do not depend on each other and can be started at the same time:

What cannot be parallelised is the permit itself, which is issued close to the day, and the simultaneous operations check, which is only meaningful against a real schedule. Those two are the last steps and they are short. If they are the only things left when the scope is agreed, the job moves quickly.

The questions that compress the timeline

Four questions asked at the first conversation remove most of the uncertainty about when the work can happen:

None of those are aviation questions, which is the point. On an operating site the flight is the easy part and the approvals are the project.

Frequently Asked Questions

Why does a half day of flying take weeks to arrange?
Because the flying is not the constraint. A contractor doing non-routine work inside an operating facility passes through prequalification, a service agreement, orientation, a reviewed safe work plan and a permit to work, and most of those exist independently of the fact that the work is aerial. Where the lead time is long it is usually prequalification, which involves a third party review and a queue. Once a vendor is in the system at a site, subsequent jobs at the same site move far faster.
Does a drone need a different permit than other contractor work?
Usually it is the same permit to work system, with the task described as aerial work. Some operators have added a specific authorisation or a standard for remotely piloted aircraft, and some treat it under elevated work or non-routine work provisions. What is consistent is that the area authority has to be able to assess the task, so the controlling factor is how clearly the scope and hazards are described rather than which form it is written on. Transport Canada requirements apply on top of the site's system, not instead of it.
Can you fly while the unit is running?
Often yes, and for some scopes it is the only useful time. Thermal inspection in particular needs equipment under load, because a cold, depressurised asset gives a radiometric camera no differential to detect. Flying while the unit runs means coordinating with operations, routing away from occupied areas, and accepting that the flight gets held or landed on a radio call. Internal capture inside a vessel or stack is the exception and is tied to the asset being open, isolated and tested.
Do we need to shut anything down for the flight?
For external capture, usually not. The exceptions tend to be specific and local rather than a unit shutdown, such as a temporary hold on a crane lift in the same area, a pause on venting that would put the aircraft in a plume, or a short stop on a conveyor or traffic route under the flight path. Those are coordination items for the day rather than scope items. Anything requiring isolation is internal work and belongs in an outage.
How much escort time should we budget?
Plan on an escort for the full duration of the crew's time in the area, including setup, briefings, the flight itself and demobilisation, and recognise that productive flight time is a minority of a site day. The practical consequence is to batch scope, meaning that if several assets need capture it is much cheaper in escort hours to do them on one mobilisation than across three visits. It is also worth confirming who the escort is in advance, because an escort pulled onto other work is a common reason a day gets cut short.
We need this inspection before a scope freeze. What is the realistic path?
Start prequalification immediately and in parallel with the scoping conversation, because it does not depend on the scope and it is the item most likely to set the date. Then work backwards from the scope freeze rather than from the outage, since findings that arrive after the work list is locked and the materials are ordered cannot change anything. If the timeline will not accommodate the full scope, the usable compromise is to prioritise the assets whose condition would change the work list and defer the rest to the post-restart window.