Flying the Site Before It Goes Out to Tender

An owner or general contractor who flies a site before the bid goes out gives every bidder the same picture of the ground. What to capture, what to put in the bid package, the licence wording that lets bidders actually use it, and why it is the cheapest defence against a site-condition claim after award.

Published 2026-10-15 · UAV Imaging Inc.

Key takeaways

Most aerial capture on a construction or earthworks project happens after someone has been awarded the work. The contractor arrives, flies the site, and finds that the ground does not match the assumption in their bid. What follows is a change order, or an argument, or both.

The cheaper sequence is to fly the site before it goes out for bid, and to hand the result to every bidder as part of the tender package. The flight costs the same either way. The difference is who is carrying the uncertainty when the prices come in.

Why the owner's flight beats the winner's flight

A bidder who cannot see the ground prices the risk of what might be there. That contingency is real money, it is invisible in the submitted number, and you pay it whether or not the risk materialises. Several bidders pricing the same unknown will price it differently, which is why two bids on the same scope can be far apart for reasons that have nothing to do with how either firm would do the work.

Put a dated, measurable record of the site in front of all of them and three things change at once. The contingency shrinks because the unknown shrinks. The bids become comparable, because the differences left are method, productivity and margin rather than each firm's private guess about the stockpile in the northeast corner. And the awarded contractor starts work from the same picture the owner had, which removes the most common opening move in a site-condition dispute.

There is a fourth benefit that only shows up later. A capture taken before anyone mobilised is the only true before image you will ever have of that site, and it is worth having for reasons that have nothing to do with the tender.

What to capture

A pre-tender flight is a scoping exercise, not a full engineering survey, and the deliverable list should reflect that. In most cases it is:

What makes this package work is the method note, not the imagery. An unlabelled picture in an appendix invites bidders to discount it. A capture with a date, a stated accuracy and a named method is a document they can rely on, and a document you can point at afterwards.

The licence wording, which is the part most packages miss

Aerial data is licensed, not simply handed over. If you commissioned the capture, the terms between you and the drone contractor decide what you may do with it, including whether you may distribute it to third parties. Issuing it to a bid list is distribution. The scope of what you own and what you may pass on is the subject of data ownership and retention on drone jobs, and it needs settling before the package is assembled rather than after a bidder asks.

Two sentences in the tender documents cover the rest:

Alongside the licence, state the disclaimer plainly. The capture represents visible surface conditions on the stated date, to the stated accuracy, and is not a geotechnical or subsurface investigation. Bidders remain responsible for their own site examination. That sentence does more to prevent an argument than any amount of additional imagery, and it is honest: a drone sees the surface, and the honest limits of aerial capture apply here exactly as they do anywhere else.

What it does to site-condition claims

A differing site-conditions claim usually turns on one question: what did the ground look like when the contract was priced, and who is in a position to prove it. When neither party has a dated record, the argument is reconstructed from photographs taken at various times by various people for other reasons, and it is resolved by negotiation rather than evidence.

A pre-tender capture changes that question into a documentary one. There is a surface, a date and a method, it was issued to the claimant as part of the documents they priced from, and the comparison against today is arithmetic rather than opinion. What makes a capture hold up in that setting is the same thing that makes any aerial record defensible: a stated date, an unedited original retained, and a method that can be described. The habit of comparing a built surface against the design surface is covered in as-built versus design surface.

It is worth being clear about scale. This does not make claims impossible, and it is not a substitute for a geotechnical program. It removes the subset of disputes that exist only because nobody wrote down what the site looked like.

Timing, and the addendum trap

The flight has to be early enough that processed deliverables are in the package when it is issued. A capture that arrives as an addendum three days before close is worse than no capture, because bidders have already priced the unknown and will not reprice on short notice, and because an addendum invites a question period extension.

Work backwards from the issue date. Allow for the flight itself, for processing and delivery, and for the weather window: Alberta sites lose days to wind, and the time from flight to deliverable is the subject of how long from flight to deliverable. Booking two to three weeks ahead of the tender issue date is comfortable for most sites. Booking the week before is a gamble on wind.

Season matters too. A site captured under snow gives bidders a less useful picture of surface conditions than the same site in September, and a winter surface carries its own caveats, covered in surveying stockpiles and sites under snow. If the tender date is fixed and the only available window is a snow-covered one, say so in the method note and let bidders weight it accordingly.

Who else uses the same capture

The tender is the reason you commissioned it, but the same dataset usually earns its keep three or four more times on the same project:

That is the real economics of a pre-tender flight. The cost sits in the owner's budget once and is recovered across the tender, the baseline and the reporting, instead of being priced into every bid as a contingency and then paid again by the winner after award.

Scoping it with a contractor

Tell the drone contractor what the capture is for. A tender capture has different priorities from a monthly progress flight: whole-site coverage matters more than tight accuracy on one corner, obliques of access and adjacency matter more than usual, and the method note is a deliverable rather than paperwork. The accuracy specification, deliverable list and other cost drivers are set out in the cost drivers on an Alberta drone survey quote, and the clauses worth writing into the request are in what to put in a drone survey RFP.

If you are issuing a project to tender in the next couple of months, the question to settle now is whether the ground is going out with the drawings or whether each bidder will be guessing at it separately. Only one of those is free.

Frequently Asked Questions

Does flying the site before tender transfer risk to the owner?
Not if the package is written properly. The capture is issued as information about visible surface conditions on a stated date, to a stated accuracy, with the explicit statement that it is not a subsurface or geotechnical investigation and that bidders remain responsible for their own site examination. What it removes is the argument that nobody knew what the ground looked like, which is an argument that has never helped an owner.
Can bidders use the drone data in their own software?
Only if the tender documents say so. Set out a bounded licence: the data may be used for preparing a bid on this project, it may not be redistributed or reused elsewhere, and unsuccessful bidders destroy or return their copies. Say separately what licence the successful bidder receives, because they will load the surface into their own civil or GIS package and work from it.
How accurate does a pre-tender capture need to be?
Usually less accurate than the construction surveys that follow. Bidders are estimating quantities and reading conditions, not setting grade. A standard photogrammetric capture with the accuracy stated in the method note is normally enough. If the project turns on a specific earthworks quantity, specify tighter accuracy and ground control for that part of the site and say which parts carry which spec.
Is the same flight useful after award?
Yes, and it is usually where most of the value ends up. The pre-tender capture is also the pre-construction baseline, so progress, quantities and any claim later are measured against a surface that predates mobilisation. Keeping the originals and the method record is what makes it usable for that second purpose.