Key takeaways
- A reflight is not one event. Weather aborts, a failed accuracy check, a scope miss and a site that was not ready have four different answers, and a contract that treats them as one thing is the reason the conversation gets expensive.
- The cost of a reflight is mobilization, not flight time. A second trip to a site two hours out costs most of what the first trip cost, while the flying itself is often the cheapest hour of the day.
- A failed accuracy check against independent checkpoints is the vendor's problem. That is what an accuracy specification means, and a contractor who will not say so in writing is quoting a different job.
- Weather is nobody's fault, which is exactly why it has to be assigned in advance. The common settlements are a shared standby rate, a free weather reflight inside the same mobilization, or weather risk priced into the original number.
- A site that was not ready is the most frequent cause and the easiest to prevent. An absent escort, a crane in the block, cars on the siding or a pile being worked all turn a booked day into a billable trip with no deliverable.
- A scope miss splits on who wrote the scope. A deliverable the contractor was told to capture and did not is theirs. A deliverable nobody asked for until after the flight is a change.
- The clause is short: define a reflight, name the four causes, assign each one, state who makes the weather call and by when, and cap standby. Half a page settled early is worth more than any amount of goodwill afterwards.
Most drone survey contracts in Alberta are a page of scope, a number and a date. They describe what happens when the flight goes to plan. They are frequently silent on the thing that actually generates the awkward phone call, which is what happens when the flight has to be done again.
It comes up more than people expect. A crew drives two hours, the ceiling drops, nothing gets flown. A survey comes back and the checkpoints do not hold the accuracy that was specified. A site turns out to have a crane parked in the middle of the block nobody mentioned. In each case somebody is about to pay for a second trip, and in each case the answer should be different.
Four causes, four different answers
Lumping these together is the root of the problem. A reflight caused by weather and a reflight caused by a failed accuracy check have nothing to do with each other, and a contract that says only "additional flights billed at standard rates" has quietly assigned all four to the client.
- Weather and conditions. Wind, ceiling, precipitation, smoke, light. Nobody's fault, entirely foreseeable as a category, and the one that needs a rule rather than a judgement.
- A failed accuracy or quality check. The data does not meet the specification it was sold against. This is the contractor's own work product failing, and it belongs to the contractor.
- A scope miss. Something that should have been captured was not. Whose it is depends entirely on who wrote the scope and what was handed over before the flight.
- The site was not ready. Access denied, escort absent, equipment running, material being moved, obstructions in the block. The crew mobilized and could not do the work it was booked for.
The money is mobilization, not flying
This is the part that surprises buyers. The flight itself is often the shortest and cheapest part of the day. What a second trip actually costs is the drive, the crew hours, the vehicle, the site check-in and orientation again, and the day that cannot be sold to anybody else.
Which is why the distinction that matters is not "did we have to fly again" but "did we have to come back". A reflight inside the same mobilization, where the crew waits two hours for the wind to drop and then flies, costs a fraction of a reflight next Tuesday. Any sensible clause treats those as different events, and the cost drivers on a survey quote are the same drivers that set the cost of repeating it. On a small parcel the effect is sharper still, because the mobilization minimum is most of the price to begin with.
Weather: nobody's fault, so assign it in advance
Alberta supplies a wide menu here. Sustained wind and gusts that put the aircraft outside its operating envelope, ceiling and visibility, summer smoke that flattens imagery and kills thermal work, cold and daylight in December, breakup and road bans that stop the truck before the aircraft is ever a question.
Three settlements are common and all three are defensible. What is not defensible is leaving it unwritten.
- Weather risk priced in. The quote carries an allowance for one weather abort, the contractor absorbs the first one, and the client pays for the second. Simple, slightly more expensive up front, and almost never argued about afterwards.
- Shared standby. If the crew mobilized on a go call that both parties made, the client pays a reduced standby or travel rate rather than a full day. The contractor carries the lost margin, the client carries the real out-of-pocket.
- Client-called go, client pays. Where the client insists on a date against the contractor's recommendation, the trip is billable. This is the fair outcome and it requires the recommendation to have been made in writing.
Tied to all three is the part most contracts miss: who makes the call, and by when. A named person on each side, a cutoff the evening before for the drive, and a second cutoff on site for the launch. Without the cutoff, every weather abort becomes an argument about whether anyone should have known.
A failed accuracy check is the contractor's
If the job was sold to a stated accuracy and the deliverable does not meet it when tested against independent checkpoints, the reflight is on the contractor. That is not a negotiating position, it is what an accuracy specification is for. Anyone who has read what a quoted accuracy figure actually means knows the claim is only meaningful if it is testable, and a testable claim has a consequence when it fails.
Two caveats keep this honest in both directions:
- The test has to be the agreed test. Independent checkpoints, in the stated coordinate system and vertical datum, on the stated geoid model. A great many apparent accuracy failures are a datum mismatch between the survey and whatever it is being compared against, and the fix for that is an hour of reprocessing rather than a flight.
- Conditions the contractor flagged and the client accepted are not failures. Where there is no correction stream or the sky is blocked, or where vegetation or standing water sits over the ground, a wider stated uncertainty agreed before the flight is the specification. Being held to a number that was explicitly qualified is not a quality failure.
A scope miss splits on who wrote the scope
The pattern is nearly always the same. The deliverable list said orthomosaic and surface. Three weeks later someone needs the volumes of the two piles behind the shop, which were outside the flown block. Nobody did anything wrong and somebody has to pay for a trip.
The split is clean if the scope was written properly:
- Named in the scope and not delivered. Contractor's reflight. No argument.
- Not named, and the contractor had the information to know it was wanted. A block boundary on a drawing, a site walk, an email naming the piles. Shared, or absorbed as goodwill, depending on how clear it was.
- Not named and genuinely new. A change, quoted and scheduled like any other work.
Which is the strongest argument available for spending an hour on the scope and deliverable clauses before the job rather than after it. The same hour prevents the related problem of two quotes that are not quoting the same job, where the cheaper number was cheaper because it was a smaller flight.
The site was not ready, which is the common one
In practice this causes more repeated trips than weather does, and unlike weather it is almost entirely preventable. The list is short and it repeats:
- The escort who was supposed to meet the crew is on another job.
- Orientation or a site induction nobody mentioned, which consumes the window.
- A crane, a drill or a service rig in the block, with an exclusion zone around it.
- A loader still working the pile that was supposed to be measured.
- Stored material, parked equipment or vehicles over the ground that mattered.
- Ground control targets removed, buried or driven over since the last visit.
- An internal approval that had not actually cleared, discovered at the gate.
Where the crew mobilized in good faith on a client confirmation and could not work, the trip is billable. That is uncomfortable to write into a contract and it is the honest position, because the alternative is a contractor pricing every job as though half the sites will not be ready. The mitigation is a site readiness confirmation sent and returned before the crew leaves, naming the escort, the access point, the block and anything shutting down. It takes five minutes and it is the cheapest insurance on the job.
There is a related case worth naming separately. Where the capture window is set by an operation rather than by the weather, as it is inside a shutdown or turnaround or on a rail siding between switches, a missed window is not a reschedule to next week. It can be a reschedule to the next outage. Those jobs need the readiness confirmation to be owned by whoever actually controls the operation, not by whoever signed the purchase order.
The clause, in plain terms
Half a page, written once, reused on every job. It needs six things:
- A definition. A reflight is a return mobilization to re-capture all or part of the scope. A delay or a second launch inside the same mobilization is not a reflight.
- The four causes, each assigned. Weather, quality failure, scope miss, site not ready. Say who pays for each in a sentence.
- The go or no-go authority and cutoffs. A named person each side, an evening cutoff for travel, an on-site cutoff for launch.
- The accuracy test that decides a quality failure. Independent checkpoints, the stated frame and geoid, the stated tolerance, and who holds the checkpoint coordinates.
- Rates, with standby capped. A travel or standby rate that is less than a full day rate, and a stated maximum, so an aborted day has a known worst case.
- Who confirms site readiness, and when. Named, with the item list, returned before the crew departs.
None of this is adversarial. It exists because both sides already know a flight will occasionally have to be repeated, and the only question is whether that gets settled on a day when nobody is annoyed or on a day when somebody is.