Who Pays When a Drone Flight Has to Be Repeated

Who absorbs a repeated drone flight under a normal Alberta survey contract: the four causes that produce a reflight, why mobilization rather than flight time is the money, and the clause that settles the question before the aborted trip rather than after it.

Published 2026-11-23 · UAV Imaging Inc.

Key takeaways

Most drone survey contracts in Alberta are a page of scope, a number and a date. They describe what happens when the flight goes to plan. They are frequently silent on the thing that actually generates the awkward phone call, which is what happens when the flight has to be done again.

It comes up more than people expect. A crew drives two hours, the ceiling drops, nothing gets flown. A survey comes back and the checkpoints do not hold the accuracy that was specified. A site turns out to have a crane parked in the middle of the block nobody mentioned. In each case somebody is about to pay for a second trip, and in each case the answer should be different.

Four causes, four different answers

Lumping these together is the root of the problem. A reflight caused by weather and a reflight caused by a failed accuracy check have nothing to do with each other, and a contract that says only "additional flights billed at standard rates" has quietly assigned all four to the client.

The money is mobilization, not flying

This is the part that surprises buyers. The flight itself is often the shortest and cheapest part of the day. What a second trip actually costs is the drive, the crew hours, the vehicle, the site check-in and orientation again, and the day that cannot be sold to anybody else.

Which is why the distinction that matters is not "did we have to fly again" but "did we have to come back". A reflight inside the same mobilization, where the crew waits two hours for the wind to drop and then flies, costs a fraction of a reflight next Tuesday. Any sensible clause treats those as different events, and the cost drivers on a survey quote are the same drivers that set the cost of repeating it. On a small parcel the effect is sharper still, because the mobilization minimum is most of the price to begin with.

Weather: nobody's fault, so assign it in advance

Alberta supplies a wide menu here. Sustained wind and gusts that put the aircraft outside its operating envelope, ceiling and visibility, summer smoke that flattens imagery and kills thermal work, cold and daylight in December, breakup and road bans that stop the truck before the aircraft is ever a question.

Three settlements are common and all three are defensible. What is not defensible is leaving it unwritten.

Tied to all three is the part most contracts miss: who makes the call, and by when. A named person on each side, a cutoff the evening before for the drive, and a second cutoff on site for the launch. Without the cutoff, every weather abort becomes an argument about whether anyone should have known.

A failed accuracy check is the contractor's

If the job was sold to a stated accuracy and the deliverable does not meet it when tested against independent checkpoints, the reflight is on the contractor. That is not a negotiating position, it is what an accuracy specification is for. Anyone who has read what a quoted accuracy figure actually means knows the claim is only meaningful if it is testable, and a testable claim has a consequence when it fails.

Two caveats keep this honest in both directions:

A scope miss splits on who wrote the scope

The pattern is nearly always the same. The deliverable list said orthomosaic and surface. Three weeks later someone needs the volumes of the two piles behind the shop, which were outside the flown block. Nobody did anything wrong and somebody has to pay for a trip.

The split is clean if the scope was written properly:

Which is the strongest argument available for spending an hour on the scope and deliverable clauses before the job rather than after it. The same hour prevents the related problem of two quotes that are not quoting the same job, where the cheaper number was cheaper because it was a smaller flight.

The site was not ready, which is the common one

In practice this causes more repeated trips than weather does, and unlike weather it is almost entirely preventable. The list is short and it repeats:

Where the crew mobilized in good faith on a client confirmation and could not work, the trip is billable. That is uncomfortable to write into a contract and it is the honest position, because the alternative is a contractor pricing every job as though half the sites will not be ready. The mitigation is a site readiness confirmation sent and returned before the crew leaves, naming the escort, the access point, the block and anything shutting down. It takes five minutes and it is the cheapest insurance on the job.

There is a related case worth naming separately. Where the capture window is set by an operation rather than by the weather, as it is inside a shutdown or turnaround or on a rail siding between switches, a missed window is not a reschedule to next week. It can be a reschedule to the next outage. Those jobs need the readiness confirmation to be owned by whoever actually controls the operation, not by whoever signed the purchase order.

The clause, in plain terms

Half a page, written once, reused on every job. It needs six things:

  1. A definition. A reflight is a return mobilization to re-capture all or part of the scope. A delay or a second launch inside the same mobilization is not a reflight.
  2. The four causes, each assigned. Weather, quality failure, scope miss, site not ready. Say who pays for each in a sentence.
  3. The go or no-go authority and cutoffs. A named person each side, an evening cutoff for travel, an on-site cutoff for launch.
  4. The accuracy test that decides a quality failure. Independent checkpoints, the stated frame and geoid, the stated tolerance, and who holds the checkpoint coordinates.
  5. Rates, with standby capped. A travel or standby rate that is less than a full day rate, and a stated maximum, so an aborted day has a known worst case.
  6. Who confirms site readiness, and when. Named, with the item list, returned before the crew departs.

None of this is adversarial. It exists because both sides already know a flight will occasionally have to be repeated, and the only question is whether that gets settled on a day when nobody is annoyed or on a day when somebody is.

Frequently Asked Questions

If the weather turns and you cannot fly, do we still get billed?
That depends on what the contract says, which is the whole point of settling it in advance. Our normal position is that a weather abort called by us before the crew departs costs nothing, an abort on site after mobilizing attracts a reduced travel or standby rate rather than a full day, and a day flown against our recommendation at the client's insistence is billable in full. All three are reasonable; what is not reasonable is discovering which one applies after the truck has already turned around.
Who pays if the survey does not hit the accuracy you quoted?
We do. An accuracy specification is only meaningful if it is testable and only honest if failing it has a consequence, so a deliverable that does not meet its stated tolerance against independent checkpoints gets re-flown at our cost. The two things that keep that fair are that the test is the agreed test in the agreed coordinate system and vertical datum, and that conditions we flagged before the flight and the client accepted, such as blocked GNSS or vegetation over the ground, are part of the specification rather than a failure against it.
Our site was not ready when the crew arrived. Is that really on us?
Usually yes, and we would rather say so plainly than price every job as though it might happen. The crew mobilized, the day cannot be resold, and the cause was on the site. The way to never pay for it is the readiness confirmation we send before the crew departs: who the escort is, where the access point is, what is in the block, what is shutting down and whether the approval has actually cleared. Five minutes on that email has saved far more trips than any clause has.
What does a repeated flight actually cost compared with the original?
Closer to the original than most people expect, because the cost is the trip rather than the flying. The drive, the crew hours, the vehicle, the check-in and the day that cannot be sold elsewhere are all incurred again, while the flight time itself is often the cheapest part of the day. That is why a delay on site is a different event from a return visit, and why the two should never be priced the same way.
Can we just add a clause that says you absorb every reflight?
You can ask for it and some contractors will sign it, but you will be paying for it in the original number, and you should want to know how much. Transferring weather and site readiness risk to the contractor means the contractor prices for the worst site and the worst week. Assigning each cause to whoever actually controls it is cheaper for both sides, because it leaves the party who can prevent a trip with the reason to prevent it.