What a Drone Survey Cannot Replace in a Geotechnical Investigation

Where aerial monitoring fits in a geotechnical programme on an Alberta slope, berm or tailings structure: what repeated capture settles about surface movement, geometry and drainage, what only boreholes and instrumentation can answer, and how the two are used together rather than against each other.

Published 2026-11-23 · UAV Imaging Inc.

Key takeaways

Aerial capture has become a normal part of monitoring a pit wall, a containment berm, a stockpile slope or a reclaimed landform in Alberta. It is quick, it covers the whole structure, and a client who has seen a good surface difference map between two captures reasonably asks the next question: how much of the geotechnical programme does this replace.

The honest answer is none of it, and that is not a hedge. A drone measures the surface of the ground. A geotechnical investigation is predominantly concerned with what is underneath the surface and what it will do under load, water and time. The capture is a genuinely valuable input to that work and it answers a different class of question.

Two questions that get conflated

It helps to separate them explicitly, because clients and sometimes vendors do not.

The second set is what a geotechnical investigation exists to answer, and it is answered by drilling, sampling, laboratory testing, in situ testing and instrumentation read over time. A surface record cannot be processed into subsurface information. It can indicate where to look, which is worth real money, and it stops there.

What repeated aerial capture genuinely contributes

Being clear about the limits makes it easier to be confident about the value, and the value is substantial on a structure of any size.

Movement: different scales, different tools

This is the comparison that causes the most confusion, because both aerial capture and geotechnical instrumentation produce something called a movement measurement, and they are not interchangeable.

A survey series detects movement that is larger than the combined uncertainty of the two captures being compared. Anything smaller is inside the noise. That makes a capture series a good detector of movement that has become significant and a poor detector of slow creep in its early stages. An instrument fixed to a monument and read continuously resolves far smaller movement at that one point, which is exactly the regime where early warning lives.

Practically, the division of labour looks like this:

Making a multi-capture series trustworthy at all is its own piece of work, and it is the part most often skipped. Permanent ground control monuments, a named datum and epoch and a frozen processing template are what separate a movement series from a sequence of unrelated surveys. Without them, a datum or processing difference between captures produces an apparent movement pattern across the whole structure, which is the failure mode that wastes the most engineering time.

What no amount of flying will answer

Worth listing plainly, because these are the questions that actually decide whether a structure is safe:

There is one more limit specific to the measurement itself. On a vegetated slope, which describes most reclaimed landforms and many older berms, the surface being measured is the top of the vegetation rather than the ground, and the offset varies with cover. That interacts badly with small movement detection, and it is the subject of the piece on what vegetation does to a survey of your ground. On slopes it is usually the reason to fly LiDAR rather than photogrammetry, and to read the resulting classified point cloud knowing that the bare earth layer is a filtering decision.

How the two are actually used together

On the Alberta sites where this works well, the arrangement is consistent and not complicated.

  1. Capture establishes the baseline geometry before or at the start of the programme, in the same frame the instruments and boreholes are tied to. Same datum, same geoid model, same epoch, stated in writing.
  2. The geotechnical investigation answers the subsurface questions through drilling, sampling, testing and instrument installation. The aerial baseline sometimes informs where to put holes, by showing where the ground is already moving or wet.
  3. Instruments are read continuously at the critical points with thresholds set by the engineer.
  4. Capture repeats on a cadence appropriate to the structure, giving change across the whole thing between instrument readings and covering everywhere no instrument exists.
  5. The engineer reads both. An anomaly in a difference surface becomes a reason to walk a specific area, to look at a nearby instrument record, or to drill. An instrument trending becomes a reason to look at the capture series for surface expression.

The closing of that loop is where the money is. A difference surface that shows a developing bulge at a toe is not a conclusion. It is an excellent and cheap reason to send a geotechnical engineer to a specific coordinate rather than on a tour of the site. Setting the capture cadence is part of the same decision, and on a monitored structure it is set by the engineer rather than by the budget cycle.

Scoping it so the deliverable is usable

A capture commissioned without the geotechnical consultant in the conversation frequently arrives in a form the consultant cannot use. Four things prevent that:

Who signs what

Worth one paragraph, because it is where the liability sits. Surface measurements and the geometry record are a survey product. A stability assessment, a factor of safety, a remediation recommendation, a dam safety review or an opinion on whether a structure is fit for purpose are professional engineering work, carried out by a qualified geotechnical engineer who takes responsibility for the opinion. A capture provider supplying measurements into that work is doing exactly the right thing, and the boundary is the same one described in the piece on who signs off drone survey data. We measure, document and hand over. The engineer concludes.

Where that boundary is respected, aerial capture is one of the better additions to a geotechnical monitoring programme available in the last decade: it covers the whole structure, it is cheap enough to repeat, and it produces a dated record that holds up later. It just does not see through ground.

Frequently Asked Questions

Can a drone survey replace boreholes on a slope or a berm?
No, and the distinction is not a technicality. A drone measures the surface of the ground. Boreholes, sampling and laboratory testing establish what the ground is made of, how strong it is, where the water table sits and where a weak layer lies, which are the parameters a stability assessment is built from. Aerial capture can tell a geotechnical engineer where to put a hole, by showing where the ground is already moving, cracking or wet, and that is genuinely useful. It cannot produce any of the information the hole produces.
Will a capture series pick up slope movement before it becomes a problem?
Only once the movement exceeds the combined uncertainty of the two captures being compared. That makes a capture series a good detector of movement that has already become significant and a poor detector of slow creep in its early stages. Early warning on slow movement is what an instrument fixed to a monument and read continuously is for. What the capture adds is coverage: it sees change everywhere on the structure, including the places nobody predicted would move and therefore did not instrument.
Can you detect seepage through a berm?
We can record indicators, which is different from measuring seepage. Visible wet ground, vegetation that is greener or more stressed than its surroundings, and where thermal is flown, temperature contrasts that can be consistent with water movement. Each of those is a reason to send somebody to a specific location, not a conclusion about what is happening inside the structure. Interpreting them, and deciding whether to install instrumentation or drill, is the geotechnical engineer's call.
How do we make sure the aerial data works with our geotechnical consultant's data?
Agree the frame with the consultant before the first flight: horizontal and vertical datum, geoid model, epoch, and the site or project grid if one is in use, matching whatever the boreholes and instruments are tied to. Then ask for the deliverables they actually work in, which is usually a point cloud, a surface model, cross sections on their chainages and contours at a stated interval, in open formats. Retrofitting a frame mismatch after several captures is possible and it is the most avoidable cost in the whole programme.
Who is responsible for saying whether the structure is stable?
A qualified geotechnical engineer, and only them. Measurements, geometry, difference surfaces and a documented capture record are a survey product that we take responsibility for. A factor of safety, a stability opinion, a remediation recommendation or a dam safety review is professional engineering work that depends on subsurface parameters no flight produces. We supply measurements into that work and we do not draw conclusions from them about stability.